How much the bug is affecting the functionality of the application?

Software Process Interview Question
Software Process Interview Question

Answer:

Ex.

High Priority and Low Severity:
Company logo is not properly displayed on their website.
High Priority and High Severity:
Suppose you are doing online shopping and filled payment information, but after submitting the form, you get a message like "Order has been cancelled."
Low Priority and High Severity:
If we have a typical scenario in which the application get crashed, but that scenario exists rarely.
Low Priority and Low Severity:
There is a mistake like "You have registered success" instead of successfully, success is written.